REGINA CORK – Building of undercarriage to adapt gear motors in sawdust dosing machine

CASE STUDY

REGINA CORK - Building of undercarriage to adapt gear motors in sawdust dosing machine

 
  • Client
  • REGINACORK
  • Execution date:
  • December 2017
  • Task:
  • Building of undercarriage to adapt gear motors in sawdust dosing machine
  • Project description

    Motor replacement and respective clutches following mechanical malfunction of planetary gearbox caused by mechanic arrest.

    It was necessary to build a new adaptive structure since the new motors did not have the same support points.

  • Work performed

    MECHANICS/IRONWORK:
    - analysis and technical drawing
    - building of metallic structure to support the new motor
    - construction of reinforced shaft for dosing propeller
    - construction of cylinder for roller bearings
    - modification and assembly of metallic structure in existing structure
    - adaptation of cylinder and shaft through modified flanges
    - assembly of geared motor and gear alignment
    - machine start-up, stress and consumption tests

 